MINISTRY OF TRANSPORT OF VIETNAM |
SOCIALIST REPUBLIC OF VIETNAM |
|
No. 1813/QD-BGTVT |
Hanoi, June 10, 2016 |
DECISION
DISCLOSURE OF THE CATEGORY OF THE ELECTRONIC TOLL COLLECTION PROJECT REGARDING TOLL BOOTHS IN CENTRAL VIETNAM, SOUTHERN VIETNAM AND TOLL BOOTHS FUNDED BY VIETINBANK ACCORDING TO THE BOO CONTRACT
MINISTER OF TRANSPORT OF VIETNAM
Pursuant to Decree No. 107/2012/ND-CP dated December 20, 2021 of the Government of Vietnam on functions, tasks, entitlements, and organizational structure of the Ministry of Transport of Vietnam;
Pursuant to Decree No. 15/2015/ND-CP dated February 14, 2015 of the Government of Vietnam on public-private partnership investment;
Pursuant to Decree No. 30/2015/ND-CP dated March 17, 2015 of the Government of Vietnam elaborating certain Articles of the Law on Bidding on Investor Selection;
Pursuant to Decision No. 1759/QD-BGTVT dated June 7, 2016 of the Minister of Transport of Vietnam approving the proposal of the electronic toll collection project regarding toll booths in Central Vietnam, Southern Vietnam, and toll booths funded by VietinBank according to the BOO Contract;
At the request of the Director - Chief of the Department of Public-Private Partnership Project Management and Investment,
HEREBY DECIDES:
Article 1. Disclosure of the category of the electronic toll collection (ETC) project regarding toll booths in Central Vietnam, Southern Vietnam, and toll booths funded by VietinBank according to the BOO Contract as an attached appendix.
Article 2. The Office of the Ministry of Transport of Vietnam is assigned to cooperate with the Information Technology Center of the Ministry of Transport of Vietnam in posting and disclosing the category of projects according to Decree No. 15/2015/ND-CP and current regulations.
Article 3. Chief of Ministry Office, Director – Chief of Department of Public-Private Partnership Project Management and Investment, Director of Department of Planning and Investment, General Director of Directorate for Roads of Vietnam, Director of Department of Construction and Transport Quality Management, Director of Information Technology Center, and Directors of relevant agencies, units shall implement this Decision./.
|
|
PP. MINISTER |
CATEGORY
THE ETC PROJECT REGARDING TOLL BOOTHS IN CENTRAL VIETNAM, SOUTHERN VIETNAM, AND TOLL BOOTHS FUNDED BY VIETINBANK ACCORDING TO THE BOO CONTRACT
(Promulgate with Decision No. 1813/QD-BGTVT dated June 10, 2016 of the Minister of Transport of Vietnam)
1. Project name and project contract type
ETC project regarding toll booths in Central Vietnam, Southern Vietnam, and toll booths funded by VietinBank according to the BOO Contract.
2. The investment aims to:
- Modernize the traffic infrastructure.
- Obtain economic and social benefits regarding the elimination of traffic jams at toll booths, saving costs for people and goods in traffic and making toll collection sources transparent.
- Assist State Agencies in managing types of vehicles in traffic, making traffic statistics supervising speed, and reducing road traffic accidents.
3. Project implementation location
BOT toll booths on expressways and highways in Central Vietnam and Southern Vietnam and all of the toll booths funded by Vietinbank.
The Investor shall select the appropriate location for the Back-End System, which includes the Data Center to be hired from service providers and the central operating system.
4. Scope, scale, technical standards, and design solutions
- Investment scope: Construct and install ETC systems at toll booths of BOT projects on expressways and highways in Central Vietnam, Southern Vietnam and toll booths funded by Vietinbank.
- Investment scale: Invest in ETC systems according to RFID technology with ISO/IEC 18000-63 standard, including the whole system of equipment, information technology infrastructure, software, training, and technology transfer to operate the toll collection system. Fundamental compositions:
a) The Front-End system:
The expectation of the completion of the ETC systems at toll booths on national highways and expressways in Central Vietnam, Southern Vietnam, and every toll booth funded by Vietinbank. Each system includes:
- The system of ETC equipment: Vehicle identification device, card reader, cameras for photos and videos, etc.
- The system of equipment and infrastructure of information and technology includes:
+ Technical infrastructure of information and technology at toll booths;
+ Software system applied at toll booths.
b) The Back-End System:
The Back-End System is developed for purposes of administration and handling of data information sent from the Front-End System and management centers of concentrated toll collection services.
The system includes:
- The host system.
- The security and network system.
- The software system for concentrated data processing, monitoring, and operation.
- The storage equipment system.
c) The system of supervision, operation, and maintenance centers
The expectation of concentrated supervision and operation centers that monitor and supervise the daily activity of the whole system from the data center (Back-End) to automatic toll booths (Front-End), detect and handle technical issues on the system 24/7; supervision and maintenance centers shall receive requests for support and maintenance from toll booths, and remotely handle them or directly at toll booths; abnormal transaction handling centers.
d) Transmission line system: The transmission line system uses optical fiber lines of telecommunications providers to connect and ensure data transmission between Front-End systems, Back-End systems, and supervision, operation, and maintenance centers.
5. Preliminary cost of total investment: 2.122 billion VND (Two thousand, one hundred and twenty-two billion VND).
6. Expectation of implementation progress
- Expectation of approval and investor selection progress for the project: from the 3rd quarter of 2016 to the 4th quarter of 2016.
- Time to construct and install equipment: expected from 2016 to 2021.
- Business period: comply with the financial plan of the project.
7. Focal agencies for contact
- Project Management Board of public-private partnership projects, Ministry of Transport of Vietnam.
- Phone number: 84-4-39410755, FAX: 84-4-39423291.
- Address: 80 Tran Hung Dao street, Hoan Kiem district, Hanoi.
---------------
This document is handled by Vinas Doc. Document reference purposes only. Any comments, please send to email: [email protected]