THE MINISTRY OF CONSTRUCTION | SOCIALIST REPUBLIC OF VIETNAM |
No. 41/2006/QĐ-BXD | Hanoi, December 29, 2006 |
DECISION
PROMULGATING VIETNAM’S CONSTRUCTION STANDARD TCXDVN 371 : 2006 “ACCEPTANCE INSPECTION OF CONSTRUCTIONAL QUALITY OF BUILDING WORKS”
THE MINISTER OF CONSTRUCTION
Pursuant to the Government's Decree No. 36/2003/NĐ-CP dated April 4th 2003, defining the functions, tasks, powers and organizational structure of the Ministry of Construction;
At the proposal of the Director of the Department of Science and Technology,
DECIDES
Article 1. Promulgate a Vietnam’s Construction Standard together with this Decision:
TCXDVN 371 : 2006 “Acceptance inspection of constructional quality of building works”
Article 2. This Decision takes effect after 15 days from the date of its publication on the Official Gazette.
Article 3. The Chief of the Ministry Office, the Director of the Department of Science and Technology and Directors of relevant organizations shall implementation this Decision./.
| PP. THE MINISTER |
ACCEPTANCE OF CONSTRUCTIONAL QUALITY OF BUILDING WORKS
Foreword
This Standard supersedes TCVN 4091:1985
The Construction standard TCXDVN 371 : 2006 “Acceptance inspection of constructional quality of building works” is issued by the Ministry of Construction together with the Decision No. .41/2006/QĐ-BXD dated December 29th 2006.
VIETNAM’S CONSTRUCTION STANDARD
ACCEPTANCE OF CONSTRUCTIONAL QUALITY OF BUILDING WORKS
1. General provisions:
2. Interpretation of terms
3. The order for inspecting the quality of constructions.
Take the following inspection steps during the construction of new or renovated works.
4. The content of construction quality inspection.
For a general contractor agreement, the supervisors of the investor shall inspect the acceptance of the general contractor and sub-contractors.
Directly carry out the acceptance inspection during the building and installation of the following subjects after receiving the written request of the contractor:
+ The name and quantity of rejected subjects;
+ The time when the contractor has to take the rejected subjects away from the construction site.
For a general contract, the supervisors of the investor shall inspect the acceptance inspection of the general contractor and sub-contractors.
Directly carry out the acceptance inspection during the building and installation of the following construction works after receiving the written request of the contractor:
+ The works to be redone;
+ The equipment to be reinstalled;
+ The defects or damage to be rectified or repaired;
+ The time limit for repair;
+ The date of reinspection.
For general contracting, the supervisors of the investor shall inspect the acceptance inspection of the general contractor and sub-contractors.
+ The works to be redone;
+ The equipment to be reinstalled;
+ The equipment to be retested;
+ The defects or damage to be rectified or repaired;
+ The time limit for repairing and retesting;
+ The date of reinspection.
The list of defects in quality is made in accordance with the form in Annex N of this Standard. The cost of the repair and rectification shall be incurred by the party that causes the defects.
If necessary, the investor may hire an independent advisor for reinspecting the rectification.
After the defects in quality, the advisor shall make an inspection record as prescribed in this Standards and send reports to the investor for reinspection.
Annex A
(Regulation)
The form of “Record of the inspection of construction quality at the construction site”
Name of investor: | SOCIALIST REPUBLIC OF VIETNAM |
| [Location and date] |
RECORD OF THE INSPECTION OF CONSTRUCTION QUALITY AT THE CONSTRUCTION SITE
The supervisors of the general contractor shall inspect the inspection of the general contractor and sub-contractors (for general contractor agreement)
Starting : .......
Ending:
At: .......................................
No. | Inspection content | Inspection result | |
1 | System of relevant technical regulations and standards | Adequate | Inadequate |
2 | Construction quality assurance system at the construction site | Available | Unavailable |
3 | The regime for responsibility and construction quality | Available | Unavailable |
4 | Capability of managers | Suitable | Unsuitable |
5 | Capability of constructional technicians | Suitable | Unsuitable |
6 | Vocational certificates of major workers | Available | Unsuitable |
7 | Capability of sub-contractors and the regime for sub-contractor management | Suitable | Unsuitable |
8 | Status of drawings | Legitimate | Illegitimate |
9 | The table of overall construction progress | Available | Unavailable |
10 | Construction method | Available | Unavailable |
11 | Regime for inspecting construction quality | Available | Unavailable |
12 | Laboratory at the site | Standard | Non-standard |
13 | Capacity of constructional equipment | Suitable | Unsuitable |
14 | Conditions for the storage of materials and equipment at the site | Satisfactory | Non-satisfactory |
15 | The regime for making and depositing documents about construction quality control | Available | Non-satisfactory |
16 | ... | ..... | ….. |
| Notes: .................................................................................................................... |
Annex B
(For reference)
Dividing construction parts and construction stages
The parts and stages of civil and industrial constructions shall be divided depending on their scale and progress. In particular:
No. | Construction parts and construction stages
|
|
1 | Base and foundation (covered under the datum)
| Soil preparation, making foundation, pile foundation, foundation framework, house foundation, underground waterproofing, flooring, etc. |
2 | Bearing structure (from the datum to the roof)
| Columns, bars, floors, walls, partitions… |
3 | Decorations and architectural completion
| Ground, floor, roof surface; waterproofing, thermal insulation, architectural shaping, plastering, internal and external finish, doors… |
4 | Technical system
| Water supply and drainage, heating; electricity, smart architecture; ventilation and air conditioning… |
9 | Elevator | Installation of the elevator cabin, hoisting system, electricity, automatic controlling system…
|
10 | Equipment fabrication and installation
| Fabrication and static installation of each equipment.
|
11 | No-load single-action test runs
| Single-action test runs of each equipment. |
12 | No-load multiple-action test runs
| No-load multiple-action test runs of each equipment cluster.
|
13 | Loaded multiple-action test runs | Loaded multiple-action test runs of each equipment cluster and each production line.
|
14 | Lightning conducting
| Lightning conducting and earthing system. |
Annex C
(Regulation)
Input inspection form
SOCIALIST REPUBLIC OF VIETNAM [Location and date] No. ……………….. INSPECTION OF PREFABRICATED COMPONENTS, EQUIPMENT, AND MATERIALS BEFORE USE Construction .................................................(name of construction)................................. Item: ...........................................(name of item)................. Location: .................................................(specify the location of the item and construction) .................................
|
1. Subjects of inspection: (specify the prefabricated components, equipment, and materials that need inspecting)
2. Participants in the acceptance inspection: (specify the organization, full names and positions of individuals)
- The person in charge of construction techniques of the constructional contractor.
Under a general contractor agreement, the supervisor of the investor shall inspect the inspection of the general contractor and sub-contractors.
3. Time of acceptance inspection:
Starting:
Ending:
At: .......................................
4. Assessment of finished works:
c) Other opinions if any.
5. Conclusion: (specify the following content)
6. Participants in the acceptance inspection: (signatures, full names, and positions of all participants)
The inspection dossier comprises:
Annex D
(Regulation)
Form of the record of acceptance inspection of construction works
SOCIALIST REPUBLIC OF VIETNAM ----------------- [Location and date] No. ACCEPTANCE INSPECTION OF CONSTRUCTION WORKS Construction: .........(name of the construction)................................................................. Item: .........name of the construction item)................................................................. Location: .................................................(specify the location of the item and construction) .................................
|
Under a general contractor agreement, the supervisor of the investor shall inspect the acceptance inspection of the general contractor and sub-contractors.
Starting:
Ending:
At: .......................................
5. Conclusion: (specify the following contents)
6. Participants in the acceptance inspection: (signatures, full names, and positions of all participants)
The inspection dossier of construction works comprises:
Annex E
(Regulation)
Form of the record of static installation inspection
SOCIALIST REPUBLIC OF VIETNAM [Location and date] No. Static installation inspection Construction .................................................(name of construction)................................. Item .................................................(name of construction item)................................. Location: .................................................(the location of the item and construction) ................................. |
Under a general contractor agreement, the supervisor of the investor shall inspect the inspection of the general contractor and sub-contractors.
3. Time of acceptance inspection:
Starting:
Ending:
At: .......................................
4. Assessment of finished works:
5. Conclusion: (specify the following contents)
6. Participants in the acceptance inspection: (signatures, full names, and positions of all participants)
Static installation inspection dossier comprises:
- The acceptance inspection record of static installation and the annexes enclosed therewith if any;
- The documents as the basis for inspection
Annex F
(Regulation)
Form of acceptance inspection of construction parts and construction stages
SOCIALIST REPUBLIC OF VIETNAM [Location and date] Construction .........................(name of the construction)................................................... Item: ....................(name of the construction item)........................................ Location: .................................................(the location of the construction item and construction) .................................
|
|
a) The investor’s party:
3. Time of acceptance inspection:
Starting:
Ending:
At: .......................................
4. Inspection of finished construction parts and construction stages:
5. Conclusion : ................................................................................................
6. Participants in the acceptance inspection: (signatures, full names, and positions of all participants)
The dossiers of acceptance inspection of construction parts and construction stages comprises:
Annex G
(Regulation)
Form of acceptance inspection record of equipment undergoing no-load single-action test runs
SOCIALIST REPUBLIC OF VIETNAM [Location and date] BIÊN BẢN SỐ NGHIỆM THU THIẾT BỊ CHẠY THỬ ĐƠN ĐỘNG KHÔNG TẢI Construction .........................(name of the construction)................................................... Item: ....................(name of the construction item)........................................ Location: .................................................(the location of the construction item and construction) .................................
|
3. Time of acceptance inspection:
Starting:
Ending:
At: .......................................
4. Assessment of the no-load single-action test run performed:
c) Other opinions if any.
5. Conclusion: (specify the following contents)
6. Participants in the acceptance inspection: (signatures, full names, and positions of all participants)
The dossier of acceptance inspection of the no-load single-action test run of equipment comprises:
- The acceptance inspection record of the equipment undergoing no-load single-action test runs;
- The documents as the basis for inspection
Annex H
(Regulation)
Form of acceptance inspection record of equipment undergoing no-load multiple-action test runs
SOCIALIST REPUBLIC OF VIETNAM [Location and date] Construction .........................(name of the construction)................................................... Item: ....................(name of the construction item)........................................ Location: .................................................(the location of the construction item and construction) .................................
|
|
For general contractor agreement, the person in charge of the supervision department of the investor shall inspect the acceptance inspection of the general contractor and sub-contractors.
Starting:
Ending:
At: .......................................
c) Other opinions if any.
5. Conclusion: (specify the following contents)
6. Participants in the acceptance inspection: (signatures, full names, and positions of all participants)
The dossier of acceptance inspection of the no-load multiple-action test run of equipment comprises:
- The acceptance inspection record of equipment undergoing no-load multiple-action test runs, and the annexes enclosed therewith if any;
- The documents as the basis for inspection
Annex J
(Regulation)
Form of acceptance inspection record of equipment undergoing loaded multiple-action test runs
SOCIALIST REPUBLIC OF VIETNAM [Location and date] Construction .........................(name of the construction)................................................... Item: ....................(name of the construction item)........................................ Location: .................................................(the location of the construction item and construction) .................................
|
|
1. The equipment system inspected includes: (specify the equipment system and testing time (starting and ending time), the position in the construction or construction item)
3. Time of acceptance inspection:
Starting:
Ending:
At: .......................................
4. Assessment of the loaded multiple-action test runs performed:
5. Conclusion: (specify the following contents)
6. Participants in the acceptance inspection: (signatures, full names, positions, and stamp)
SUPERVISORY CONTRACTOR (Signature, full name, position, and stamp) | INVESTOR (Signature, full name, position, and stamp)
|
CONSTRUCTION DESIGNING CONTRACTOR (Signature, full name, position, and stamp)
| CONSTRUCTIONAL CONTRACTOR (Signature, full name, position, and stamp)
|
The dossier of acceptance inspection of equipment undergoing loaded multiple-action test runs comprises:
Annex K
(Regulation)
Form of the record of acceptance inspection finished constructions or construction items for putting into use.
Name of investor | SOCIALIST REPUBLIC OF VIETNAM [Location and date] |
ACCEPTANCE INSPECTION OF FINISHED CONSTRUCTIONS OR CONSTRUCTION ITEMS FOR PUTTING INTO USE
Starting:
Ending:
At: .......................................
CONSTRUCTIONAL CONTRACTOR (Signature, full name, position, and stamp)
| INVESTOR (Signature, full name, position, and stamp)
|
CONSTRUCTION DESIGNING CONTRACTOR (Signature, full name, position, and stamp)
| CONSTRUCTIONAL CONTRACTOR (Signature, full name, position, and stamp)
|
The dossier of acceptance inspection comprises:
Annex L
(Regulation)
The form of the List of changes compared to the approved design
Construction: ........................ Item: ............................. | SOCIALIST REPUBLIC OF VIETNAM [Location and date] |
LIST OF CHANGES COMPARED TO THE APPROVED DESIGN
No. | Changed contents and number of approved drawings | Reasons for changes | The approving agency
| Name, number, and date of the written approval | Notes | |
..... ….. …..
| ….. ….. ….. | ..... ….. ….. | ….. ….. ….. | ….. ….. ….. | ..... ….. …..
| |
REPRESENTATIVE OF SUPERVISORY CONTRACTOR (signature, full name, and position)
| REPRESENTATIVE OF INVESTOR (Signature, full name, position, and stamp)
| |||||
REPRESENTATIVE OF DESIGNING CONTRACTOR (Signature, full name, position, and stamp) | REPRESENTATIVE OF MAIN CONSTRUCTIONAL CONTRACTOR (Signature, full name, position, and stamp)
|
Annex M
(Regulation)
List of unfinished works
Construction: ........................ Item: ............................. | SOCIALIST REPUBLIC OF VIETNAM [Location and date] |
LIST OF UNFINISHED WORKS
No. | Unfinished work | Estimated (bidden) value | Executing unit | Time of completion
| Notes | ||||
..... ….. …..
| ….. ….. ….. | ….. ….. ….. | ….. ….. ….. | ….. ….. …..
| ….. ….. ….. | ||||
REPRESENTATIVE OF SUPERVISORY CONTRACTOR (signature, full name, and position)
| REPRESENTATIVE OF INVESTOR (Signature, full name, position, and stamp)
|
|
| ||||||
REPRESENTATIVE OF DESIGNING CONTRACTOR (signature, full name, and position)
| REPRESENTATIVE OF MAIN CONSTRUCTIONAL CONTRACTOR (Signature, full name, position, and stamp)
|
|
|
Annex N
(Regulation)
List of quality defects
Construction: Item: | SOCIALIST REPUBLIC OF VIETNAM [Location and date] |
LIST OF QUALITY DEFECTS
No. | Part (equipment)
| Status | Repairing unit | Completion date | Notes |
…..
| ….. | ….. | ….. | ….. | ….. |
…..
| ….. | ….. | ….. | ….. | ….. |
…..
| ….. | ….. | ….. | ….. | ….. |
|
|
|
|
|
|
|
|
|
|
|
|
REPRESENTATIVE OF SUPERVISORY CONTRACTOR (signature, full name, and position)
| REPRESENTATIVE OF INVESTOR (Signature, full name, position, and stamp)
|
REPRESENTATIVE OF DESIGNING CONTRACTOR (signature, full name, and position)
| REPRESENTATIVE OF MAIN CONSTRUCTIONAL CONTRACTOR (Signature, full name, position, and stamp)
|
Annex P
(Regulation)
List of documents serving the acceptance inspection of construction or construction item for handing over and putting into use
Construction: ........................ Item: ............................. | SOCIALIST REPUBLIC OF VIETNAM [Location and date] |
LIST OF DOCUMENTS SERVING THE ACCEPTANCE INSPECTION OF CONSTRUCTION OR CONSTRUCTION ITEM FOR HANDING OVER AND PUTTING INTO USE
No.
| List of documents | Preparing unit | |||
.....
| ..... | ..... | |||
REPRESENTATIVE OF INVESTOR (signature, full name, and position) | REPRESENTATIVE OF DESIGNING CONTRACTOR (signature, full name, and position) | REPRESENTATIVE OF MAIN CONSTRUCTIONAL CONTRACTOR (Signature, full name, position, and stamp)
|
Annex Q
(Regulation)
Name of investor | LIST OF DOCUMENTS ABOUT THE COMPLETION OF CONSTRUCTIONS OR CONSTRUCTION ITEMS |
A. Legal documents
THE DOSSIER MAKER
File gốc của Decision No 41/2006/QD-BXD of December 29, 2006, promulgating Vietnam’s construction standard TCXDVN 371 : 2006 “acceptance inspection of constructional quality of building works” đang được cập nhật.
Decision No 41/2006/QD-BXD of December 29, 2006, promulgating Vietnam’s construction standard TCXDVN 371 : 2006 “acceptance inspection of constructional quality of building works”
Tóm tắt
Cơ quan ban hành | Bộ Xây dựng |
Số hiệu | 41/2006/QD-BXD |
Loại văn bản | Quyết định |
Người ký | Nguyễn Văn Liên |
Ngày ban hành | 2006-12-29 |
Ngày hiệu lực | 2007-02-04 |
Lĩnh vực | Xây dựng - Đô thị |
Tình trạng | Đã hủy |